鋪設曲靖路面加筋網的下承層應表面平整、壓實,并清除表面堅硬凸出物。
The laying of the pavement reinforcement network should be under the surface layer formation, compaction, and removal of hard surface protrusions.
路面加筋網鋪設前應按設計幅寬在鋪筑層畫出白線,用鐵釘固定加筋網端部(每米寬用釘8根,均勻距離固定)。
Pavement reinforcement before the laying of the width of the pavement should be drawn in the pavement layer to draw white lines, with nails fixed end of the reinforcement net (8 meters wide with nails, uniform distance from the fixed).
固定好加筋網端部后,人工將加筋網緩緩向前拉鋪,每10米長人工拉緊和調直一次,直至一卷鋪完,再鋪下一卷,操作同前。
After fixing the end of the reinforced net, the artificial net will be pulled forward slowly. Every 10 meters long will be tightened and straightened until the roll is finished. Then roll the next roll.
路面加筋網鋪設時,必須拉緊展平插釘固定,并與路基面密貼不得有皺褶扭曲。
When laying the pavement reinforcement mesh, it must be tightened and flattened and fixed with the nails, and the pavement surface shall not be wrinkled and twisted.
鋪完一卷用壓路機沿前進方向從起點碾壓一遍即可鋪設后續(xù)加筋網。
Paved a roll with the roller along the way from the starting point of rolling again to lay the follow-up reinforcement.
鋪完一卷后再整體檢查一次鋪設質量,然后再鋪下一段,鋪設時接縫搭接長度10cm~15cm,并用鐵釘或木偰固定后再繼續(xù)鋪設。
After laying out a volume and then check the overall quality of a laying, and then pave the next section, when the lap laying lap length of 10cm ~ 15cm, and fixed with nails or wood and then continue laying.